In the Matter of Certificate of Convenience and Necessity to Operate as a Public Utility Rendering Service, or for an Exemption from PSC Regulation
2003Dockets
Docket No: 03-035-04
In the Matter of the Application of the Formal Complaint of Dammeron Valley Water Works vs. Utah Power and Light
Docket No: 03-2410-01
In the Matter of the Application of Broadweave Networks of Utah, LLC for a Certificate of Public Convenience and Necessity to Provide Local Exchange and Facilities-Based Interexchange Services within the State of Utah
Docket No: 03-2403-02
In the Matter of the Petition of WWC Holding Co., Inc. for Arbitration of Interconnection Agreement
Docket No: 03-049-62
In the Matter of Qwest Corporation’s Land Development Agreements (LDA) Tariff Provisions
Docket No: 03-049-19
In the Matter of the Petition by Autotel for Arbitration of an Interconnection Agreement with Qwest Pursuant to Section 252(b) of the Telecommunications Act
Docket No: 03-057-05
In the Matter of the Application of Questar Gas Company to Adjust Rates for Natural Gas Service in Utah
Docket No: 03-2035-02
In the Matter of the Application of PacifiCorp for Approval of Its Proposed Electric Service Schedules & Electric Service Regulatio
Docket No: 03-2035-01
In the Matter of the Acknowledgment of PacifiCorp Integrated Resource Plan 2003
Docket No: 03-035-T10
In the Matter of Schedule 37- Avoided Cost Purchases from Qualifying Facilities
Docket No: 03-035-38
In the Matter of the Petition of US Magnesium LLC for Approval of a Contract for the Sale of Capacity and Energy from its Existing and Proposed QF Facilities
Docket No: 03-035-29
In the Matter of the Application of PacifiCorp for a Certificate of Convenience and Necessity Authorizing Construction of the Currant Creek Power Project
Docket No: 03-035-28
In the Matter of Comcast Cable Communications, INC., a Pennsylvania Corporation vs. PacifiCorp, dba UTAH POWER, an Oregon Corporation
Docket No: 03-035-19
In the Matter of the Application of US magnesium LLC for Determination of Long-Term Economic Development Rates and Conditions of Interruptible Service
Docket No: 03-035-14
In the Matter of the Application of PacifiCorp for Approval of an IRP-based Avoided Cost Methodology for QF Projects Larger than One Megawatt
Docket No: 03-035-01
In the Matter of the Divisions Annual Review and Evaluation of the Electric Lifeline Program, HELP