Docket No: 17-035-52
Formal Complaint under Schedule 38, Clenera, LLC on behalf of 1.21 GW LLC against Rocky Mountain Power
For questions regarding documents not linked call 801-530-6714
Date | Description |
---|---|
February 6, 2018 | Erratum Order |
February 6, 2018 | Order |
January 16, 2018 | Reporter’s Transcript Re: December 21, 2017 Exhibit A – Clenera Exhibit 1 Exhibit B – Clenera Exhibit 2 Exhibit C – RMP Response to the Complaint Exhibit D – RMP Interconnection Summary |
December 21, 2017 | Audio of Hearing December 21, 2017 |
November 21, 2017 | Order Denying Motion to Dismiss and Notice of Hearing |
October 24, 2017 | Clenera Response to PacifiCorp Motion to Dismiss |
October 23, 2017 | Rocky Mountain Power’s Response to the Formal Complaint of Clenera, LLC and Motion to Dismiss |
October 23, 2017 | Comments from the Division of Public Utilities |
September 29, 2017 | Notice and Amendment to Action Request |
September 27, 2017 | Change to Filing |
September 25, 2017 | Notice of Filing and Comment Period |
September 22, 2017 | Action Request, Due: October 23, 2017 |
September 22, 2017 | Formal Complaint |