Docket No: 17-035-40
Application of Rocky Mountain Power for Approval of a Significant Energy Resource Decision and Voluntary Request for Approval of Resource Decision
For questions regarding documents not linked call 801-530-6716
Date | Description |
---|---|
October 3, 2024 | Order |
August 13, 2024 | Rocky Mountain Power’s Reply Comments on Report for Calendar Year 2023 |
July 30, 2024 | Redacted Amended Comments from the Division of Public Utilities Amended Comments from the Division of Public Utilities [CONFIDENTIAL] |
July 29, 2024 | Redacted Comments from the Division of Public Utilities Comments from the Division of Public Utilities [CONFIDENTIAL] |
July 29, 2024 | Redacted Comments from the Office of Consumer Services Comments from the Office of Consumer Services [CONFIDENTIAL] |
May 28, 2024 | Notice of Filing and Comment Period |
May 24, 2024 | Action Request, Due: July 22, 2024 |
May 23, 2024 | Rocky Mountain Power’s New Wind and Transmission Report for Calendar Year 2023 RMP Attachment 1 – RMP’s New Wind and Transmission Report for CY 2023 [CONFIDENTIAL] |
September 8, 2023 | Order |
August 8, 2023 | Redacted Rocky Mountain Power’s Reply Comments on Report for Calendar Year 2022 Rocky Mountain Power’s Reply Comments on Report for Calendar Year 2022 [CONFIDENTIAL] RMP Attachment 1 – Updated Report 2022 [CONFIDENTIAL] |
August 8, 2023 | Redacted Reply Comments from the Office of Consumer Services Reply Comments from the Office of Consumer Services [CONFIDENTIAL] |
July 25, 2023 | Redacted Comments from the Division of Public Utilities Comments from the Division of Public Utilities [CONFIDENTIAL] |
July 25, 2023 | Comments from the Office of Consumer Services |
June 26, 2023 | Amended Notice of Filing and Comment Period |
June 22, 2023 | Division of Public Utilities’ Request for Extension of Time |
May 25, 2023 | Notice of Filing and Comment Period |
May 25, 2023 | Action Request, Due: June 23, 2023 |
May 24, 2023 | Rocky Mountain Power’s New Wind and Transmission Report for Calendar Year 2022 RMP Attachment 1 – RMP’s New Wind and Transmission Report for CY 2022 [CONFIDENTIAL] |
August 1, 2022 | Order |
July 15, 2022 | Redacted Rocky Mountain Power’s Reply Comments on Report for Calendar Year 2021 Rocky Mountain Power’s Reply Comments on Report for Calendar Year 2021 [CONFIDENTIAL] |
June 30, 2022 | Comments from the Division of Public Utilities DPU Attachment A – Tab (i) Final Project Costs [CONFIDENTIAL] DPU Attachment A – Tab (ii) Calculated Projected PTC Benefits Comparison [CONFIDENTIAL] DPU Attachment A – Tab (iii) Estimated Energy Loss Due to Unrealized Energy Generation [CONFIDENTIAL] DPU Attachment A – Tab (viii) O&M Costs [CONFIDENTIAL] |
May 27, 2022 | Amended Notice of Filing and Comment Period |
May 24, 2022 | Division of Public Utilities’ Request for Extension of Time |
May 5, 2022 | Notice of Filing and Comment Period |
April 29, 2022 | Action Request, Due: May 31, 2022 |
April 29, 2022 | Rocky Mountain Power’s New Wind and Transmission Report for Calendar Year 2021 RMP Attachment 1 – RMP’s New Wind and Transmission Report for CY 2021 [CONFIDENTIAL] |
July 21, 2021 | Order |
June 17, 2021 | Rocky Mountain Power’s Reply Comments RMP Attachment 1 – Revenue from Wind Projects [CONFIDENTIAL] |
June 3, 2021 | Correspondence from Gary L. Widerburg, Re: the Utah Association of Energy Users’ Motion to Deviate from Electronic Filing Requirement |
June 2, 2021 | Utah Association of Energy Users’ Redacted Initial Comments on Rocky Mountain Power’s New Wind and Transmission Report Utah Association of Energy Users’ Initial Comments on Rocky Mountain Power’s New Wind and Transmission Report [CONFIDENTIAL] |
June 2, 2021 | Utah Association of Energy Users’ Motion to Deviate from Electronic Filing Requirement |
June 2, 2021 | Comments from the Office of Consumer Services |
May 27, 2021 | Comments from the Division of Public Utilities |
May 3, 2021 | Notice of Filing and Comment Period |
April 29, 2021 | Action Request, Due: May 28, 2021 |
April 29, 2021 | Rocky Mountain Power’s New Wind and Transmission Report for Calendar Year 2020 RMP Attachment A – New Wind and Transmission Report for Calendar Year 2020 [CONFIDENTIAL] |
November 15, 2018 | Order Denying Motion to Stay |
November 6, 2018 | Utah Association of Energy Users’ Reply in Support of Motion for Stay Pending Appeal |
October 29, 2018 | Rocky Mountain Power’s Opposition to Utah Association of Energy Users’ Motion for Stay Pending Appeal |
October 29, 2018 | Declaration of Chad A. Teply in Support of Rocky Mountain Power’s Opposition to Utah Association of Energy Users’ Motion for Stay Pending Appeal |
October 26, 2018 | Response of the Interwest Energy Alliance to Utah Association of Energy Users’ Motion to Stay Commission Order |
October 22, 2018 | Order on Reporting Requirements |
October 15, 2018 | Reply Comments from Rocky Mountain Power Re: Proposed Reporting System RMP Attachment A – Final Project Costs |
October 12, 2018 | Utah Association of Energy Users’ Motion for Stay Pending Review Exhibit A – Rocky Mountain Power’s Response to Petitioner’s Motion for Enlargement of Time to File Brief |
October 1, 2018 | Comments from the Office of Consumer Services |
October 1, 2018 | Comments of Western Resource Advocates on Reporting Requirements |
October 1, 2018 | Comments from the Division of Public Utilities DPU Attachment I – Division’s Recommendations for Reporting on the Wind and Transmission Projects to the Company Attachment A |
September 4, 2018 | Notice of Filing and Comment Period |
August 31, 2018 | Action Request Due: October 1, 2018 |
August 31, 2018 | Rocky Mountain Power’s Compliance Filing to Present its Proposed Reporting Requirements RMP Attachment A – Proposed Reporting System for the Combined Projects |
August 8, 2018 | Order on Review |
August 7, 2018 | Order on Review |
August 6, 2018 | Rocky Mountain Power’s Response in Opposition to Utah Association of Energy Users’ Application for Reconsideration and Rehearing of Commission Order Issued June 22, 2018 |
August 3, 2018 | Rocky Mountain Power’s Response to Joint Petition for Review or Clarification |
July 20, 2018 | Application of Utah Association of Energy Users for Reconsideration and Rehearing of Commission Order Issued June 22, 2018 |
July 19, 2018 | Joint Petition for Review or Clarification Certificate of Service |
July 9, 2018 | Public Comments from July 9, 2018 |
June 25, 2018 | Comments from Protect Our Winters, POWDR Resorts, Snowbird, et al. |
June 22, 2018 | Public Comments from June 22, 2018 |
June 22, 2018 | Order |
June 18, 2018 | Public Comments from June 18, 2018 |
June 15, 2018 | Public Comments from June 15, 2018 |
June 13, 2018 | Public Comments from June 13, 2018 |
June 12, 2018 | Public Comments from June 12, 2018 |
June 12, 2018 | Notice of Determination that Additional Time is Warranted and Intent to Issue Order |
June 12, 2018 | Reporter’s Transcript Re: June 1, 2018 RMP Cross Exhibit 22 – B. Mullins Comments Oregon PUC, January 2017 PGE IRP RMP Cross Exhibit 23 – Order Sigurd to Red Butte Line RMP Cross Exhibit 24 – Order, 2014 General Rate Case RMP Cross Exhibit 25 – Order, CPCN, Populus to Terminal Line RMP Cross Exhibit 26 – Order RMP 2011 General Rate Case RMP Cross Exhibit 27 – RFP Testimony Excerpt from F. Steve Knudsen |
June 12, 2018 | Reporter’s Transcript Re: May 31, 2018 RMP Cross Exhibit 2 – Order, Mona-Oquirrh RMP Cross Exhibit 3 – Division Comments 2015 IRP Update RMP Cross Exhibit 5 – DPU Questions for October 11, 2017 Technical Conference RMP Cross Exhibit 6 – Response to DPU Data Request 8.1 RMP Cross Exhibit 7 – Response to DPU Data Request 12.4 RMP Cross Exhibit 19 – RMP Data Request 1.3 RMP Cross Exhibit 21 – Transcript Excerpts of Chehalis Proceeding RMP Cross Exhibit 11 – Chehalis Order RMP Cross Exhibit 15 – Currant Creek Order DPU Cross Exhibit 9 – 2017 IRP Update, Henry Hub Forecast versus Inflation WRA Exhibit E – 2017 IRP Update Summer Capacity Load and Resource Balance EV2020 Projects and FOTs Removed Reporter’s Transcript Re: May 31, 2018 [PROPRIETARY] RMP Cross Exhibit 20 – PIRA Executive Summary [PROPRIETARY] RMP Cross Exhibit 30 – UAE Data Request 5.18 [PROPRIETARY] |
June 12, 2018 | Reporter’s Transcript Re: May 30, 2018 DPU Cross Exhibit 5 – Staff Final Comments UAE Cross Exhibit 2 – Rebuttal Testimony of Wayne Oliver |
June 12, 2018 | Reporter’s Transcript Re: May 29, 2018 DPU Confidential Exhibit 1 – RMP Gas Price Forecast [PROPRIETARY] DPU Cross Exhibit 2 – Redacted Rebuttal Testimony of Rick T. Link DPU Cross Exhibit 3 – Oregon PUC, Shortlist not Acknowledged DPU Cross Exhibit 4 – 2007 Integrated Resource Plan Update UIEC Cross Exhibit 1 – Letter, Dated May 11, 2015 from RMP to PSC, Clements Testimony UAE Cross Exhibit 1 – Annual Energy Outlook 2018, EIA |
June 11, 2018 | Public Comments from June 11, 2018 |
June 8, 2018 | Public Comments from June 8, 2018 |
June 7, 2018 | Public Comments from June 7, 2018 |
June 6, 2018 | Public Comments from June 6, 2018 |
June 5, 2018 | Public Comments from June 5, 2018 |
June 1, 2018 | Audio of Hearing held June 1, 2018 |
May 31, 2018 | Audio of Hearing held May 31, 2018 Witnesses (In order of Appearance): Joni Zenger – Division of Public Utilities Charles E. Peterson- Division of Public Utilities David Thomson – Division of Public Utilities Daniel Peaco – Division of Public Utilities Bela Vastag – Office of Consumer Services Philip Hayet – Office of Consumer Services Donna Ramas – Office of Consumer Services Nancy Kelly – Western Resource Advocates |
May 30, 2018 | Audio of Hearing held May 30, 2018 Witnesses (In order of Appearance): Rick Link – Rocky Mountain Power Wayne Oliver – Independent Evaluator, Merrimack Energy Group, Inc. Rick Vail – Rocky Mountain Power Nikki Kobliha – Rocky Mountain Power Chad Teply – Rocky Mountain Power Joelle Steward – Rocky Mountain Power Gregory Jenner – Interwest Energy Alliance Joni Zenger – Division of Public Utilities |
May 29, 2018 | Audio of Hearing held May 29, 2018 Witnesses (In order of Appearance): Cindy Crane – Rocky Mountain Power Rick Link – Rocky Mountain Power |
May 25, 2018 | Partial Joinder of Joint Motion to Strike Surrebuttal Testimony Certificate of Service |
May 25, 2018 | Joint Motion to Strike the Surrebuttal Testimony of Rocky Mountain Power’s Witnesses and for Expedited Treatment |
May 22, 2018 | Notice of Appearance of Counsel – Re: Sophie Hayes for Western Resource Advocates Appendix A Re: Sophie Hayes for Western Resource Advocates Certificate of Service |
May 22, 2018 | Notice of Withdrawal of Counsel Re: Sophie Hayes for Utah Clean Energy Certificate of Service |
May 18, 2018 | Cover Letter WRA Surrebuttal Workpapers Certificate of Service |
May 15, 2018 | Redacted Rocky Mountain Power Surrebuttal Testimonies and Exhibits RMP Vail WP1 – Path Definitions RMP Vail WP2 – Power Flow Plots RMP Vail WP3 – 2020 Energy Vision Summary RMP Link WP4 – Nom Rev Req2 RMP Link WP5 – Price Policy Scenarios RMP Link WP6 – Trans in Status Quo Calculations RMP Link WP7 – UT Schedule 37 Comparison RMP Link WP8 – WECC Solar Capacity Chart RMP Surrebuttal Testimonies and Exhibits [PROPRIETARY] RMP Steward WP9 – Combined Projects [PROPRIETARY] RMP JRS WP10 – Combined Projects [PROPRIETARY] RMP Link WP11 – PaR Summary Reports [PROPRIETARY] RMP Link WP12 – SO Summary Reports [PROPRIETARY] RMP Link WP13 – Uinta PaR Summary Reports [PROPRIETARY] RMP Link WP14 – Uinta SP Summary Reports [PROPRIETARY] RMP Link WP15 – FSLW No Uinta Summary Details [PROPRIETARY] RMP Link WP16 – PVRRd Remove Uinta [PROPRIETARY] RMP Link WP17 – P_R17-FSNU-LN [PROPRIETARY] RMP Link WP18 – P_R17-FSNU-MM [PROPRIETARY] RMP Link WP19 – R17-FSNU-LN [PROPRIETARY] RMP Link WP20 – R17-FSNU-MM [PROPRIETARY] RMP Link WP21 – Scalar Analysis Detail Summary [PROPRIETARY] RMP Link WP22 – Scalar Sensitivity Charts [PROPRIETARY] RMP Link WP23 – Solar Portfolio [PROPRIETARY] RMP Link WP24 – P_R17-Base-LN [PROPRIETARY] RMP Link WP25 – P_R17-Base-MM [PROPRIETARY] RMP Link WP26 – P_R17-BaseSC-LN [PROPRIETARY] RMP Link WP27 – P_R17-BsCO-MM [PROPRIETARY] RMP Link WP28 – P_R17-FSLW-LN [PROPRIETARY] RMP Link WP29 – P_R17-FSLW-MM [PROPRIETARY] RMP Link WP30 – P_R17-FSLWSC-LN [PROPRIETARY] RMP Link WP31 – P_R17-FSLWSC-MM [PROPRIETARY] RMP Link WP32 – P_S17-Base-HH [PROPRIETARY] RMP Link WP33 – P_S17-Base-HM [PROPRIETARY] RMP Link WP34 – P_S17-Base-HN [PROPRIETARY] RMP Link WP35 – P_S17-Base-LH [PROPRIETARY] RMP Link WP36 – P_S17-Base-LM [PROPRIETARY] RMP Link WP37 – P_S17-Base-LN [PROPRIETARY] RMP Link WP38 – P_S17-Base-MH [PROPRIETARY] RMP Link WP39 – P_S17-Base-MM [PROPRIETARY] RMP Link WP40 – P_S17-Base-MN [PROPRIETARY] RMP Link WP41 – P_S17-BaseSC-LN [PROPRIETARY] RMP Link WP42 – P_S17-BaseSC-MM [PROPRIETARY] RMP Link WP43 – P_S17-CAPC-LN [PROPRIETARY] RMP Link WP44 – P_S17-CAPC-MM [PROPRIETARY] RMP Link WP45 – P_S17-Port2-LN [PROPRIETARY] RMP Link WP46 – P_S17-SOCO2-MM [PROPRIETARY] RMP Link WP47 – P_S17-SOCSC-LN [PROPRIETARY] RMP Link WP48 – P_S17-SOCSC-MM [PROPRIETARY] RMP Link WP49 – P_S17-SOL-HH [PROPRIETARY] RMP Link WP50 – P_S17-SOL-HM [PROPRIETARY] RMP Link WP51 – P_S17-SOL-HN [PROPRIETARY] RMP Link WP52 – P_S17-SOL-LH [PROPRIETARY] RMP Link WP53 – P_S17-SOL-MH [PROPRIETARY] RMP Link WP54 – P_S17-SOL-MM [PROPRIETARY] RMP Link WP55 – P_S17-SOL-MN [PROPRIETARY] RMP Link WP56 – P_S17-SOLP1-LH [PROPRIETARY] RMP Link WP57 – P_S17-SOLP1-LM [PROPRIETARY] RMP Link WP58 – P_S17-SOLP1-LN [PROPRIETARY] RMP Link WP59 – P_S17-SOLP1-MM [PROPRIETARY] RMP Link WP60 – P_S17-SOLP1-MN [PROPRIETARY] RMP Link WP61 – P_S17-SOLP2-HH [PROPRIETARY] RMP Link WP62 – P_S17-SOLP2-HM [PROPRIETARY] RMP Link WP63 – P_S17-SOLP2-HN [PROPRIETARY] RMP Link WP64 – P_S17-SOLP2-LM [PROPRIETARY] RMP Link WP65 – P_S17-SOLP2-LN [PROPRIETARY] RMP Link WP66 – P_S17-SOLP2-MH [PROPRIETARY] RMP Link WP67 – P_S17-SOLSCP2C-MM [PROPRIETARY] RMP Link WP68 – P_S17-SOLSCP2-MM [PROPRIETARY] RMP Link WP69 – P_S17-SOSCLP2C-LN [PROPRIETARY] RMP Link WP70 – P_S17-SOSCLP2-LN [PROPRIETARY] RMP Link WP71 – R17-Base-LN [PROPRIETARY] RMP Link WP72 – R17-BaseSC-LN [PROPRIETARY] RMP Link WP73 – R17-BaseSC-MM [PROPRIETARY] RMP Link WP74 – R17-BsCO-MM [PROPRIETARY] RMP Link WP75 – R17-FSLW-LN [PROPRIETARY] RMP Link WP76 – R17-FSLW-MM [PROPRIETARY] RMP Link WP77 – R17-FSLWSC-LN [PROPRIETARY] RMP Link WP78 – R17-FSLWSC-MM [PROPRIETARY] RMP Link WP79 – S17-Base-HH [PROPRIETARY] RMP Link WP80 – S17-Base-HM [PROPRIETARY] RMP Link WP81 – S17-Base-HN [PROPRIETARY] RMP Link WP82 – S17-Base-LH [PROPRIETARY] RMP Link WP83 – S17-Base-LM [PROPRIETARY] RMP Link WP84 – S17-Base-LN [PROPRIETARY] RMP Link WP85 – S17-Base-MH [PROPRIETARY] RMP Link WP86 – S17-Base-MM [PROPRIETARY] RMP Link WP87 – S17-Base-MN [PROPRIETARY] RMP Link WP88 – S17-BaseSC-LN [PROPRIETARY] RMP Link WP89 – S17-BaseSC-MM [PROPRIETARY] RMP Link WP90 – S17-CAPC-LN [PROPRIETARY] RMP Link WP91 – S17-CAPC-MM [PROPRIETARY] RMP Link WP92 – S17-Port2-LN [PROPRIETARY] RMP Link WP93 – S17-SOCO2-MM [PROPRIETARY] RMP Link WP94 – S17-SOCSC-LN [PROPRIETARY] RMP Link WP95 – S17-SOCSC-MM [PROPRIETARY] RMP Link WP96 – S17-SOL-HH [PROPRIETARY] RMP Link WP97 – S17-SOL-HM [PROPRIETARY] RMP Link WP98 – S17-SOL-HN [PROPRIETARY] RMP Link WP99 – S17-SOL-LH [PROPRIETARY] RMP Link WP100 – S17-SOL-MH [PROPRIETARY] RMP Link WP101 – S17-SOL-MM [PROPRIETARY] RMP Link WP102 – S17-SOL-MN [PROPRIETARY] RMP Link WP103 – S17-SOLP1-LH [PROPRIETARY] RMP Link WP104 – S17-SOLP1-LM [PROPRIETARY] RMP Link WP105 – S17-SOLP1-LN [PROPRIETARY] RMP Link WP106 – S17-SOLP1-MM [PROPRIETARY] RMP Link WP107 – S17-SOLP1-MN [PROPRIETARY] RMP Link WP108 – S17-SOLP2-HH [PROPRIETARY] RMP Link WP109 – S17-SOLP2-HM [PROPRIETARY] RMP Link WP110 – S17-SOLP2-HN [PROPRIETARY] RMP Link WP111 – S17-SOLP2-LM [PROPRIETARY] RMP Link WP112 – S17-SOLP2-LN [PROPRIETARY] RMP Link WP113 – S17-SOLP2-MH [PROPRIETARY] RMP Link WP114 – S17-SOLSCP2C-LN [PROPRIETARY] RMP Link WP115 – S17-SOLSCP2C-MM [PROPRIETARY] RMP Link WP116 – S17-SOLSCP2-LN [PROPRIETARY] RMP Link WP117 – S17-SOLSCP2-MM [PROPRIETARY] |
May 15, 2018 | Prefiled Second Surrebuttal Testimony of Nancy L. Kelly on behalf of Western Resource Advocates WRA Attachment A – WRA Data Request 5.2 WRA Attachment B – WRA Data Request 6.1 WRA Attachment C – 2017 IRP Update Summary WRA Attachment D – WRA Data Request 3.1 WRA Attachment E – The Wall Street Journal Article WRA Attachment F – Pacific Power States Estimated Annual Carbon Prices Certificate of Service |
May 15, 2018 | Second Surrebuttal Testimony of Kate Bowman on behalf of Utah Clean Energy UCE Attachment A – Exhibit 3 – Calculation of Change in CO2 Benefits Certificate of Service |
April 19, 2018 | Notice of Appearance of Counsel Re: Hunter Holman for Utah Clean Energy Appendix A Re: Hunter Holman for Utah Clean Energy |
April 18, 2018 | Filings in Support of Daniel Peaco Testimony for DPU – Table 5 filed April 17, 2018 [PROPRIETARY] Filings in Support of Daniel Peaco Testimony for DPU- Tables 1, 6, and 7 filed April 17, 2018 [PROPRIETARY] |
April 17, 2018 | Prefiled Response Testimony of Nancy L. Kelly on behalf of Western Resource Advocates Certificate of Service |
April 17, 2018 | Redacted Supplemental Rebuttal Testimony of Bradley G. Mullins on behalf of the Utah Association of Energy Users and the Utah Industrial Energy Consumers Supplemental Rebuttal Testimony of Bradley G. Mullins on behalf of the Utah Association of Energy Users and the Utah Industrial Energy Consumers [PROPRIETARY] |
April 17, 2018 | Redacted Second Rebuttal Testimony of Philip Hayet for the Office of Consumer Services OCS Exhibit Hayet 2.1 – OCS Data Request 5.8 OCS Workpapers Hayet 4 – Forecast Tables OCS Workpapers Hayet 5 – OCS Data Request 1.27 OCS Workpapers Hayet 6 – OCS Data Request 16.7 OCS Workpapers Hayet 7 – UIEC Data Request 2.3 Certificate of Service Second Rebuttal Testimony of Philip Hayet for the Office of Consumer Services [PROPRIETARY] Certificate of Service [PROPRIETARY] OCS Workpapers Hayet 1 -Levelized Wind Tables [PROPRIETARY] OCS Workpapers Hayet 2- Solar Tables [PROPRIETARY] OCS Workpapers Hayet 3- Cap Cost Table 9 [PROPRIETARY] |
April 17, 2018 | Second Rebuttal Testimony of Bela Vastag for the Office of Consumer Services Certificate of Service |
April 17, 2018 | Second Rebuttal Testimony of Donna Ramas for the Office of Consumer Service Certificate of Service |
April 17, 2018 | Supplemental Rebuttal and Surrebuttal Testimony of David Thomson for the Division of Public Utilities Certificate of Service DPU Thomson Exhibit: 4.1 – GRC Rate Base DPU Thomson Exhibit: 4.2 – OCS Data Request 13.1 |
April 17, 2018 | Redacted Supplemental Rebuttal and Surrebuttal Testimony of Dr. Joni S. Zenger for the Division of Public Utilities Certificate of Service Supplemental Rebuttal and Surrebuttal Testimony of Dr. Joni S. Zenger for the Division of Public Utilities [PROPRIETARY] Certificate of Service [PROPRIETARY] |
April 17, 2018 | Redacted Supplemental Rebuttal and Surrebuttal Testimony of Charles E. Peterson for the Division of Public Utilities Certificate of Service Supplemental Rebuttal and Surrebuttal Testimony of Charles E. Peterson for the Division of Public Utilities [PROPRIETARY] Certificate of Service [PROPRIETARY] |
April 17, 2018 | Redacted Supplemental Rebuttal and Surrebuttal Testimony of Daniel Peaco for the Division of Public Utilities Certificate of Service Supplemental Rebuttal and Surrebuttal Testimony of Daniel Peaco for the Division of Public Utilities [PROPRIETARY] Certificate of Service [PROPRIETARY] |
April 2, 2018 | Appendix A Re: Stacy Tellinghuisen for Western Resource Advocates |
March 27, 2018 | Notice and Order |
March 26, 2018 | Division of Public Utilities’ Reply in Support of its Objection to the Completeness of Rocky Mountain Power’s Filing Certificate of Service |
March 19, 2018 | Rocky Mountain Power’s Response in Opposition to the Division of Public Utilities’ Objection to Completeness of Filing |
March 16, 2018 | Surrebuttal Testimony of Nancy L. Kelly on behalf of Western Resource Advocates Certificate of Service |
March 16, 2018 | Surrebuttal Testimony of Kate Bowman on behalf of Utah Clean Energy Certificate of Service |
March 16, 2018 | Surrebuttal Testimony of Daniel Peaco on behalf of the Division of Public Utilities Certificate of Service |
March 14, 2018 | Public Comments from March 14, 2018 |
March 12, 2018 | Public Comments from March 12, 2018 |
March 12, 2018 | Notice of Objection and Briefing Schedule |
March 9, 2018 | Division of Public Utilities’ Objection to the Completeness of Rocky Mountain Power’s Filing Certificate of Service |
March 8, 2018 | Public Comments from March 8, 2018 |
March 7, 2018 | Public Comments from March 7, 2018 |
March 6, 2018 | Public Comments from March 6, 2018 |
March 6, 2018 | Rocky Mountain Power’s Response to the Utah Association of Energy Users’ Request to Receive Highly Confidential Final Report of Independent Examiner |
March 6, 2018 | Order Clarifying Amended Scheduling Order |
March 5, 2018 | Public Comments from March 5, 2018 |
March 5, 2018 | Affidavit, Oath and Verification of Gregory F. Jenner for the Interwest Energy Alliance |
March 5, 2018 | Correspondence from Justin Jetter, Attorney for the Division of Public Utilities |
March 2, 2018 | Public Comments from March 2, 2018 |
March 2, 2018 | Supplemental Answer Testimony of Gregory F. Jenner for the Interwest Energy Alliance Certificate of Service |
March 2, 2018 | Correspondence from Yvonne Hogle for Rocky Mountain Power Re: Utah Association of Energy Users’ Request for Copy of Highly Confidential Version of IE Report |
March 1, 2018 | Public Comments from March 1, 2018 |
February 28, 2018 | Public Comment from February 28, 2018 |
February 28, 2018 | Utah Association of Energy Users’ Request to Receive Highly Confidential Final Report of Independent Examiner |
February 28, 2018 | Correspondence from Gary L. Widerburg Re: Merrimack Energy Group, Inc.’s Motion to Deviate from Electronic Filing Requirement |
February 27, 2018 | Notice |
February 27, 2018 | Redacted Final Report of the Independent Evaluator Merrimack Energy Group, Inc. Highly Confidential Final Report of the Independent Evaluator Merrimack Energy Group, Inc. [PROPRIETARY] |
February 27, 2018 | Merrimack Energy Group, Inc.’s Motion to Deviate from Electronic Filing Requirement |
February 23, 2018 | Rocky Mountain Power’s Corrected Second Supplemental Direct Testimony and Exhibits Corrected Exhibit RTLink-2SS Corrected Exhibit RTLink-3SS Corrected Exhibit RTLink-4SD Corrected Exhibit RTLink-5SD Corrected Table 2-SD, Table 3-SD, Figure 5 FSL Results Summary File – VOM Adjusted [PROPRIETARY] Corrected EV2020 Second Supplemental Results Summary File – VOM Adjusted [PROPRIETARY] |
February 23, 2018 | Correspondence from Gary L. Widerburg Re: Rocky Mountain Power’s Motion to Deviate from Utah Admin. Code R746-1-601(2)(d)(i), (ii) and (iii), and R746-1-203(1)(c) |
February 21, 2018 | Public Comments from February 21, 2018 |
February 21, 2018 | Reporter’s Transcript Re: February 6, 2018 |
February 16, 2018 | Rocky Mountain Power’s Motion to Deviate from Utah Admin. Code R746-1-601(2)(d)(i), (ii) and (iii), and R746-1-203(1)(c) and Redacted Second Supplemental Direct Testimony Rocky Mountain Power’s Motion to Deviate from Utah Admin. Code R746-1-601(2)(d)(i), (ii) and (iii), and R746-1-203(1)(c) and Second Supplemental Direct Testimony [PROPRIETARY] Exhibit RTLink-1SS – Wind Resources [PROPRIETARY] Exhibit RTLink-5SS – Bid Number [PROPRIETARY] Exhibit RTLink-14SS Part 1, 2, and 3 [PROPRIETARY] Exhibit CATeply-5SS – Itemized Tables Capital Details for Shortlisted BTA’s [PROPRIETARY] Replacement Exhibits CATeply [PROPRIETARY] Sub Exhibits CATeply [PROPRIETARY] PaR Stochastic Summary Reports [PROPRIETARY] Linked Repower Sensitivity Case [PROPRIETARY] SO Summary Reports [PROPRIETARY] Transmission-Gateway [PROPRIETARY] EV2020 Second Supp Results Summary File [PROPRIETARY] OMAG Sensitivity [PROPRIETARY] SO Input – Output R17-Base-HH [PROPRIETARY] SO Input Output R17-Base-HM [PROPRIETARY] SO Input Output R17-Base-HN [PROPRIETARY] SO Input Output R17-Base-LH [PROPRIETARY] SO Input Output R17-Base-LM [PROPRIETARY] SO Input Output R17-Base-LN [PROPRIETARY] SO Input Output R17-Base-MH [PROPRIETARY] SO Input Output R17-Base-MM [PROPRIETARY] SO Input Output R17-Base-MN [PROPRIETARY] SO Input Output R17-FSGE1-LN [PROPRIETARY] SO Input Output R17-FSGE1-MM [PROPRIETARY] SO Input Output R17-FSIE-MM [PROPRIETARY] SO Input Output R17-FSLW-HH [PROPRIETARY] SO Input Output R17-FSLW-HM [PROPRIETARY] SO Input Output R17-FSLW-HN [PROPRIETARY] SO Input Output R17-FSLW-LH [PROPRIETARY] SO Input Output R17-FSLW-LM [PROPRIETARY] SO Input Output R17-FSLW-LN [PROPRIETARY] SO Input Output R17-FSLW-MH [PROPRIETARY] SO Input Output R17-FSLW-MM [PROPRIETARY] SO Input Output R17-FSLW-MN [PROPRIETARY] SO Input Output R17-FSOPT-LN [PROPRIETARY] SO Input Output R17-FSOPT-MM [PROPRIETARY] SO Input Output R17-FSREP-LN [PROPRIETARY] SO Input Output R17-FSREP-MM [PROPRIETARY] SO Input Output R17-FSSR-LN [PROPRIETARY] SO Input Output R17-FSSR-MM [PROPRIETARY] SO Input Output R17-FSWS-LN [PROPRIETARY] PaR Input Output P_R17-Base-HH [PROPRIETARY] PaR Input Output P_R17-Base-HM [PROPRIETARY] PaR Input Output P_R17-Base-HN [PROPRIETARY] PaR Input Output P_R17-Base-LH [PROPRIETARY] PaR Input Output P_R17-Base-LM [PROPRIETARY] PaR Input Output P_R17-Base-LN [PROPRIETARY] PaR Input Output P_R17-Base-MH [PROPRIETARY] PaR Input Output P_R17-Base-MM [PROPRIETARY] PaR Input Output P_R17-Base-MN [PROPRIETARY] PaR Input Output P_R17-FSIE-MM [PROPRIETARY] PaR Input Output P_R17-FSLW-HH [PROPRIETARY] PaR Input Output P_R17-FSLW-HM [PROPRIETARY] PaR Input Output P_R17-FSLW-HN [PROPRIETARY] PaR Input Output P_R17-FSLW-LH [PROPRIETARY] PaR Input Output P_R17-FSLW-LM [PROPRIETARY] PaR Input Output P_R17-FSLW-LN [PROPRIETARY] PaR Input Output P_R17-FSLW-MH [PROPRIETARY] PaR Input Output P_R17-FSLW-MM [PROPRIETARY] PaR Input Output P_R17-FSLW-MN [PROPRIETARY] PaR Input Output P_R17-FSREP-LN [PROPRIETARY] PaR Input Output P_R17-FSREP-MM [PROPRIETARY] PaR Input Output P_R17-FSSR-LN [PROPRIETARY] PaR Input Output P_R17-FSSR-MM [PROPRIETARY] PaR Input Output P_R17-FSWS-LN [PROPRIETARY] PaR Input Output P_R17-FSWS-MM [PROPRIETARY] |
February 16, 2018 | Public Comments from February 16, 2018 |
February 13, 2018 | Order Granting Motion to Vacate Remaining Schedule and Amended Scheduling Order |
February 8, 2018 | Correspondence from the Division of Public Utilities Re: the Availability of the Division of Public Utilities’ Witness, Dan Peaco Exhibit A: Wyoming Suspension Order |
February 6, 2018 | Public Comments from February 6, 2018 |
February 6, 2018 | Audio of Oral Argument held February 6, 2018 |
January 29, 2018 | Notice of Oral Argument on Motion to Vacate Remaining Schedule and Order Suspending Deadlines |
January 26, 2018 | Division of Public Utilities’ and Office of Consumer Services’ Reply to Rocky Mountain Power’s Response to Motion to Vacate Remaining Schedule and Request for Expedited Treatment Certificate of Service |
January 26, 2018 | The Utah Industrial Energy Consumers’ Reply Comments in Support of Motion to Vacate Remaining Schedule and Request for Expedited Treatment |
January 26, 2018 | The Utah Association of Energy Users’ Reply Comments in Support of Motion to Vacate Remaining Schedule |
January 26, 2018 | Rocky Mountain Power’s Reply to the Utah Association of Energy Users and the Utah Industrial Energy Consumers’ Support for Motion to Vacate Schedule |
January 25, 2018 | Utah Association of Energy Users’ Comments in Support of Motion to Vacate Schedule |
January 24, 2018 | Rocky Mountain Power’s Response to Motion to Vacate Remaining Schedule |
January 24, 2018 | Utah Industrial Energy Consumers’ Memorandum in Support of Motion to Vacate Remaining Schedule and Request for Expedited Treatment |
January 22, 2018 | Public Comments from January 22, 2018 |
January 22, 2018 | Appendix A Re: Keith Oliver from Merrimack Energy |
January 19, 2018 | Erratum Notice |
January 19, 2018 | Order Granting Motion to Vacate Remaining Schedule |
January 19, 2018 | Motion to Vacate Remaining Schedule and Request for Expedited Treatment Certificate of Service |
January 19, 2018 | Cover Letter Rocky Mountain Power Replacement Exhibit RMP_RTL-2SD [PROPRIETARY] |
January 18, 2018 | Appendix A Re: Edward L. Selgrade |
January 17, 2018 | Appendix A Re: Wayne Oliver |
January 17, 2018 | Public Comments from January 17, 2018 |
January 16, 2018 | Redacted Supplemental Direct and Rebuttal Testimony of Cindy A. Crane, Chad A. Teply, Rick A. Vail, Rick T. Link, Joelle R. Steward, and Nikki L. Kobliha for Rocky Mountain Power Exhibit RMP (JRS-2SD-4SD) – Capital Structure and Cost Exhibit RMP (RTL-4SD) – – SO Model and PaR Model Annual Results ($ million) Exhibit RMP (RTL-5SD) – – Estimated Annual Revenue Requirement Results ($ million) Load Forecast Update vs. 2017 IRP Figure 2-SD and Figure 3-SD Henry Hub Prices Figure 4-SD CO2 Price Data East West 1217 LowGas- 0CO2 East West 2017 LowGas-MCO2 East West 2017 LowGas-HCO2 East West 1217 HighGas-0CO2 East West 1217 HighGas-MCO2 East West 1217 HighGas-HCO2 East West 2017 MedGas-MCO2 East West 1217 MedGas-HCO2 Endure Price V9 12.29.2017 East West Historic Workpapers to Joelle R. Steward’s Testimony Supplemental Direct and Rebuttal Testimony of Rocky Mountain Power [PROPRIETARY] RMP Exhibit CAT-5SD [PROPRIETARY] RMP Exhibit RTL -1SD [PROPRIETARY] RMP Exhibit RTL -3SD [PROPRIETARY] PaR Summary Reports [PROPRIETARY] Repower [PROPRIETARY] SO Summary Reports [PROPRIETARY] Transmission Project [PROPRIETARY] PaR Input Output [PROPRIETARY] OMAG Sensitivity [PROPRIETARY] |
January 16, 2018 | Rebuttal Testimony of Bradley Mullins for Association of Energy Users and Exhibit 2.1 |
January 16, 2018 | Rebuttal Testimony of Bela Vastag for Office of Consumer Services Exhibit 1.1R Vastag– NTTG Comments and Responses Rebuttal Testimony of Donna Ramas for Office of Consumer Services Rebuttal Testimony of Philip Hayet for Office of Consumer Services Certificate of Service for Vastag, Ramas and Hayet Testimonies |
January 16, 2018 | Rebuttal Testimony of David Thomson for the Division of Public Utilities Certificate of Service |
January 16, 2018 | Rebuttal Testimony of Dr. Joni S. Zenger for the Division of Public Utilities Certificate of Service |
January 16, 2018 | Rebuttal Testimony of Kate Bowman for Utah Clean Energy Certificate of Service |
January 12, 2018 | Public Comments from January 12, 2018 |
January 11, 2018 | Appendix A – Re: Carlo Bencomo-Jasso of Daymark Energy Advisors |
December 26, 2017 | Public Comments from December 26, 2017 |
December 20, 2017 | Public Comments from December 20, 2017 |
December 19, 2017 | Appendix A Re: John J. Miller |
December 11, 2017 | Public Comments from December 11, 2017 |
December 7, 2017 | Public Comments from December 7, 2017 |
December 6, 2017 | Replacement Direct Testimony of Kate Bowman on behalf of Utah Clean Energy Certificate of Service |
December 5, 2017 | Direct Testimony of Kate Bowman on behalf of Utah Clean Energy Exhibit 1 – Climate Science Special Report Exhibit 2 – Direct Testimony of Gregory Jenner from 11/20/2017 Wyoming PSC Certificate of Service |
December 5, 2017 | Redacted Direct Testimony and Exhibits of Bradley G. Mullins for the Utah Association of Energy Users Direct Testimony and Exhibits of Bradley G. Mullins [PROPRIETARY] Exhibit 1.3 to Direct Testimony of Bradley G. Mullins [PROPRIETARY] Exhibit 1.4 to Direct Testimony of Bradley G. Mullins [PROPRIETARY] |
December 5, 2017 | Redacted Direct Testimony of Philip Hayet for the Office of Consumer Services Exhibit Hayet OCS 2.1D – Qualifications of Philip Hayet, Vice President Direct Testimony of Philip Hayet for the Office of Consumer Services [PROPRIETARY] Workpapers – 20% Tax Rate + $9 PTC – Ekola 250 RFPBM V13G_EPC_03312017-30YR-GW4_FINAL Workpapers – 20% Tax Rate + $9 PTC – Energy Gateway GM 2017 03 13 w Bonus Workpapers – 20% Tax Rate + $9 PTC – Gateway Results Direct Testimony_20% Tax Rate+$9 PTC Workpapers – 20% Tax Rate + $9 PTC – Gateway_IRP Data Workpapers – 20% Tax Rate + $9 PTC – McFadden 110 RFPBM V13G_EPC_03312017_30YR-GW4_FINAL Workpapers – 20% Tax Rate + $9 PTC – TB Flats I 250 RFPBM V13G_EPC_03312017-30YR-GW4_FINAL Workpapers – 20% Tax Rate + $9 PTC – TB Flats II 250 RFPBM V13G_EPC_03312017-30YR-GW4_FINAL Workpapers – 20% Tax Rate + $9 PTC – Wind Summary Data Workpapers – 20% Tax Rate – Ekola 250 RFPBM V13G_EPC_03312017-30YR-GW4_FINAL Workpapers – 20% Tax Rate – Energy Gateway GM 2017 03 13 w Bonus Workpapers – 20% Tax Rate – TB Flats II 250 RFPBM V13G_EPC_03312017-30YR-GW4_FINAL Workpapers – 20% Tax Rate – Wind Summary Data Workpapers – Lost Bonus – Energy Gateway GM 2017 03 13 w Bonus_noBONUS Workpapers – Lost Bonus – Gateway Results Direct Testimony.notes.noBONUS Workpapers – Lost Bonus – Gateway_IRP Data_noBONUS Workpapers – Miscellaneous – Gateway Results Direct Testimony.ocs_calcs-CONF Hayet Workpapers – DPU Data Request 4.3 Hayet Workpapers – OCS Data Request 1.9 Hayet Workpapers – OCS Data Request 1.10 Hayet Workpapers – OCS Data Request 1.27 Hayet Workpapers – OCS Data Request 1.42 Hayet Workpapers – OCS Data Request 1.51 Hayet Workpapers – OCS Data Request 8.5 Hayet Workpapers – OCS Data Request 8.12 Hayet Workpapers – OCS Data Request 8.15 Hayet Workpapers – PIIC Data Request 15 Hayet Workpapers – 17-035-39 – OCS Data Request 1.12 Hayet Workpapers – 17-035-39 – OCS Data Request 1.62 Certificate of Service to Redacted Direct Testimony of Vastag, Ramas, and Hayet for the Office of Consumer Services Certificate of Service to Proprietary Direct Testimony of Ramas and Hayet for the Office of Consumer Services |
December 5, 2017 | Redacted Direct Testimony of Donna Ramas for the Office of Consumer Services Appendix I – Qualifications of Donna Ramas Direct Testimony of Donna Ramas for the Office of Consumer Services [PROPRIETARY] Certificate of Service to Redacted Direct Testimony of Vastag, Ramas, and Hayet for the Office of Consumer Services Certificate of Service to Proprietary Direct Testimony of Ramas and Hayet for the Office of Consumer Services |
December 5, 2017 | Direct Testimony of Bela Vastag for Office of Consumer Services Certificate of Service to Redacted Direct Testimony of Vastag, Ramas, and Hayet for the Office of Consumer Services |
December 5, 2017 | Prefiled Direct Testimony of Nancy L. Kelly on behalf of Western Resource Advocates Exhibit A – Qualifications of Nancy L. Kelly Exhibit B – Moody’s Investors Service Article Certificate of Service |
December 5, 2017 | Answer Testimony of Gregory F. Jenner filed on behalf of the Interwest Energy Alliance Exhibit A – Bio of Gregory F. Jenner Exhibit B – GTM Article Certificate of Service |
December 5, 2017 | Direct Testimony of Charles E. Peterson for the Division of Public Utilities Exhibit A – 100 Percent Forecast Exhibit B – Forecast Certificate of Service |
December 5, 2017 | Direct Testimony of David Thomson for the Division of Public Utilities Certificate of Service |
December 5, 2017 | Direct Testimony of Dr. Joni S. Zenger on behalf of the Division of Public Utilities Certificate of Service |
December 5, 2017 | Redacted Direct Testimony of Daniel Peaco on behalf of the Division of Public Utilities Direct Testimony of Daniel Peaco on behalf of the Division of Public Utilities [PROPRIETARY] Exhibit A – Qualifications of Daniel Peaco Certificate of Service |
December 5, 2017 | Redacted Direct Testimony of Robert A. Davis on behalf of the Division of Public Utilities Direct Testimony of Robert A. Davis on behalf of the Division of Public Utilities [PROPRIETARY] Certificate of Service |
November 28, 2017 | Public Comments from November 28, 2017 |
November 27, 2017 | Public Comments from November 27, 2017 |
November 24, 2017 | Public Comments from November 24, 2017 |
November 22, 2017 | Public Comments from November 22, 2017 |
November 21, 2017 | Public Comments from November 21, 2017 |
November 20, 2017 | Public Comments from November 20, 2017 |
November 17, 2017 | Public Comments from November 17, 2017 |
November 16, 2017 | Public Comments from November 16, 2017 |
November 15, 2017 | Public Comments from November 15, 2017 |
November 14, 2017 | Public Comments from November 14, 2017 |
November 13, 2017 | Public Comments from November 13, 2017 |
November 7, 2017 | Public Comments from November 9, 2017 |
November 7, 2017 | Order Denying Motion to Stay |
November 6, 2017 | Appendix A Re: Steven S. Michel and John Nielsen – Western Resource Advocates |
October 25, 2017 | Utah Industrial Energy Consumers’ Supplement to the Certificate of Service in its Reply in Support of Its Motion to Stay Proceedings Certificate of Service |
October 25, 2017 | Utah Industrial Energy Consumers’ Reply in Support of Its Motion to Stay Proceedings |
October 20, 2017 | Order Granting Pro Hac Vice Admission of Adam Lowney |
October 20, 2017 | Order Granting Pro Hac Vice Admission of Katherine McDowell |
October 16, 2017 | Reply of the Utah Division of Public Utilities to Responses to Utah Industrial Energy Consumers’ Motion to Stay Proceedings Certificate of Service |
October 16, 2017 | Rocky Mountain Power’s Reply to Office of Consumer Services’ Response to the Utah Industrial Energy Consumers’ Motion to Stay Proceedings |
October 11, 2017 | Copy of EV2020 Reliability Testimony Support [PROPRIETARY] |
October 11, 2017 | Audio for October 11, 2017 Technical Conference Sign-In for October 11, 2017 Technical Conference |
October 10, 2017 | Wyoming Transmission Map for October 11, 2017 Technical Conference |
October 10, 2017 | Load and Resource Balance Sheet Presentation for October 11, 2017 Tech Conference |
October 10, 2017 | Rocky Mountain Power’s Response to Utah Industrial Energy Consumers’ Motion to Stay Proceedings |
October 10, 2017 | Appendix A Re: Lisa Tormoen Hickey and Mitch M. Longson |
October 10, 2017 | Appendix A Re: Phillip J. Russell |
October 10, 2017 | Utah Association of Energy Users’ Joinder in UIEC’s Motion to Stay Proceedings and Office’s Response in Support |
October 6, 2017 | Office of Consumer Services’ Response to the Utah Industrial Energy Consumers’ Motion to Stay Proceedings Certificate of Service |
October 6, 2017 | Office of Consumer Services’ Questions for the October 11, 2017 Technical Conference |
October 5, 2017 | Division of Public Utilities’ Questions for the October 11, 2017 Technical Conference |
October 3, 2017 | Public Service Commission Staff Question for the October 11, 2017 Technical Conference |
October 3, 2017 | Motion and Consent of Sponsoring Local Counsel for Pro Hac Vice Admission of Adam Lowney |
October 3, 2017 | Motion and Consent of Sponsoring Local Counsel for Pro Hac Vice Admission of Katherine McDowell |
September 27, 2017 | Appendix A Re: Bradley Mullins |
September 27, 2017 | Order Granting Intervention of Western Resource Advocates |
September 22, 2017 | Order Granting Intervention of the Utah Industrial Energy Consumers |
September 22, 2017 | Utah Industrial Energy Consumers’ Motion to Stay Proceedings Exhibit A – Rocky Mountain Power Wants to spend billions on wind energy in Wyoming Article Exhibit B – Our WIND ENERGY Resources Report Exhibit C – cnet article – From coal mind to wind farm Exhibit D – Failed Nevada Experimental Energy Plant Mosts Millions article Exhibit E – Salt Lake Tribune County Leaders chide RMP for putting wind projects in Wyoming instead of rural Utah |
September 21, 2017 | Order Granting Intervention of Utah Clean Energy |
September 14, 2017 | Notice of Technical Conference |
September 12, 2017 | Order Granting Pro Hac Vice Admission of Lisa Tormoen Hickey |
September 12, 2017 | Appendix A Re: Jennifer E. Gardner and Nancy Kelly |
September 6, 2017 | Petition for Leave to Intervene of Western Resource Advocates |
September 6, 2017 | Order Granting Intervention of the Interwest Energy Alliance |
September 1, 2017 | Petition to Intervene of Utah Industrial Energy Consumers Exhibit A |
August 31, 2017 | Appendix A Re: Emma Rieves |
August 31, 2017 | Appendix A Re: Sarah Wright, Kate Bowman, and Sophie Hayes |
August 31, 2017 | Utah Clean Energy Petition to Intervene |
August 31, 2017 | Order Granting Intervention of Nucor Steel-Utah, a Division of Nucor Corporation |
August 25, 2017 | Motion and Consent of Sponsoring Local Counsel for Admission Pro Hac Vice of Lisa Tormoen Hickey, Tormoen Hickey LLC Proposed Order Admitting Counsel Pro Hac Vice |
August 23, 2017 | Amended Notice of Technical Conferences |
August 22, 2017 | Rocky Mountain Power’s Motion for Amended Procedural Schedule |
August 16, 2017 | Petition to Intervene of the Interwest Energy Alliance |
August 15, 2017 | Order Granting Intervention of the Utah Association of Energy Users |
August 14, 2017 | Amended Notice of Technical Conferences |
August 11, 2017 | Rocky Mountain Power’s Motion for Amended Procedural Schedule |
August 10, 2017 | Appendix A Re: Jeremy R. Cook, Peter J. Mattheis, and Eric J. Lacey |
August 10, 2017 | Petition to Intervene of Nucor Steel-Utah, a Division of Nucor Corporation |
August 8, 2017 | Appendix A Re: Ricky Conant |
August 7, 2017 | Appendix A Re: Aliea Afnan, Waine P. Whittier, Dwarakesh Nallan, Jeffrey D. Bower, and Samantha Bobo |
July 27, 2017 | Scheduling Order and Notices of Technical Conference and Hearing |
July 25, 2017 | Appendix A Re: Kathleen A. Kelly, Sam Brandin, Tina Bennett, and Stephen Wood |
July 25, 2017 | Appendix A Re: Gary A. Dodge |
July 25, 2017 | Petition to Intervene of the Utah Association of Energy Users |
July 18, 2017 | Email Correspondence |
July 17, 2017 | Appendix A Re: Donna Ramas |
July 13, 2017 | Appendix A Re: Randall J. Falkenberg |
July 13, 2017 | Appendix A Re: Dan Koehler and Daniel Peaco |
July 13, 2017 | Appendix A Re: Philip Hayet, Randy A. Futral, and Leah J. Wellborn |
July 13, 2017 | Post-Scheduling Conference Follow-Up |
July 12, 2017 | Scheduling Conference Sign-In Sheet |
July 3, 2017 | Notice of Scheduling Conference |
June 30, 2017 | Office of Consumer Services’ Request for Alternate Date for Scheduling Conference Certificate of Service |
June 30, 2017 | Action Request, Due: July 31, 2017 |
June 30, 2017 | Application for Approval of a Significant Energy Resource Decision and Voluntary Request for Approval of Resource Decision RMP Exhibit RTL-1 [PROPRIETARY] RMP Exhibit RTL-2 6-30-17 RMP Exhibit RTL-3 6-30-17 RMP Exhibit RTL-4 6-30-17 RMP Exhibit JKL-2 6-30-17 RMP Exhibit JKL-3 6-30-17 RMP Exhibit JKL-4 6-30-17 Direct Testimony and Exhibits of RMP [PROPRIETARY] Exhibit CAT-1 Subexhibits [PROPRIETARY] Exhibit CAT-2 Subexhibits [PROPRIETARY] Exhibit CAT-3 Subexhibits [PROPRIETARY] Rick Link Workpapers [PROPRIETARY] Jeffrey Larsen Workpapers [PROPRIETARY] |
June 23, 2017 | Public Notice |