Docket No: 17-035-37

Rocky Mountain Power’s 2017 Avoided Cost Input Changes Quarterly Compliance Filing

For questions regarding documents not linked call 801-530-6714

Date Description
April 16, 2018 Tariff Approval Letter from the PSC
April 13, 2018 Rocky Mountain Power’s Compliance Filing
March 15, 2018 Tariff Approval Letter from the PSC
March 14, 2018 Comments from the Division of Public Utilities
February 22, 2018 Action Request, Due: March 14, 2018
February 22, 2018 Quarterly Compliance Filing – 2017.Q4 Avoided Cost Input Changes
Appendix B.1
Appendix B.2
Appendix B.3
Appendix B.4
Appendix B.5
Appendix B.6
Appendix C
Workpapers – QF Queue Partial Displacement Calculation
Workpapers – FOT Partial Displacement
January 23, 2018 Order
January 10, 2018 Comments from the Division of Public Utilities
January 3, 2018 Amended Action Request, Due: January 10, 2018
December 21, 2017 Action Request Due: January 22, 2018
December 21, 2017 Rocky Mountain Power Q3 Compliance Filing
RMP Appendix B.1 Avoided Cost Prices
RMP Appendix B.2 Table 2 Avoided Energy Costs
RMP Appendix B.3 – Avoided Cost Prices
RMP Appendix C – Utah Quarterly Compliance Filing Step Study

Workpapers
UT 2017.Q3 – FOT Partial Displacement with Links
UT 2017.Q3 – QF Partial Displacement Calculation
UT 2017.Q3 – FOT Partial Displacement
December 18, 2017 Reporter’s Transcript Re: December 4, 2017
Exhibit 1 Notice of Workshop State of Washington Utilities and Transportation Commission
Exhibit 3 Disposition: Matter Reopened for comments Public Utility Commission of Oregon
Exhibit 4 Opening Comments Public Utility Commission of Oregon
December 4, 2017 Audio of Hearing held December 4, 2017
November 21, 2017 Surrebuttal Testimony of Kate Bowman on behalf of Utah Clean Energy
Surrebuttal Testimony of Ken Dragoon on behalf of Utah Clean Energy
Certificate of Service
November 21, 2017 Surrebuttal Testimony of John Lowe for the Renewable Energy Coalition
Exhibit A – REC Data Request 1.25
November 21, 2017 Surrebuttal Testimony of Neal Townsend for the Renewable Energy Coalition
November 21, 2017 Surrebuttal Testimony of Daniel J. MacNeil for Rocky Mountain Power
November 21, 2017 Surrebuttal Testimony of Abdinasir M. Abdulle, Ph.D. for the Division of Public Utilities
Certificate of Service
October 31, 2017 Rebuttal Testimony of Ken Dragoon for Utah Clean Energy

Rebuttal Testimony of Kate Bowman for Utah Clean Energy
UCE Data Request 2.1
Certificate of Service
October 31, 2017 Rebuttal Testimony of Daniel J. MacNeil for Rocky Mountain Power
MacNeil Workpaper – Testimony Support
MacNeil Workpaper – AC Study Summary Signed Queue Only
MacNeil Workpaper – Avoided Cost Study-Solar F
MacNeil Workpaper – Avoided Cost Study-Solar T
MacNeil Workpaper – Avoided Cost Study-Thermal
MacNeil Workpaper – Avoided Cost Study-Wind
MacNeil Workpaper – QF Pricing Detail-Solar F
MacNeil Workpaper – QF Pricing Detail-Solar T
MacNeil Workpaper – QF Pricing Detail-Thermal
MacNeil Workpaper – QF Pricing Detail-Wind
MacNeil Workpaper 1a – GRID AC Thermal [PROPRIETARY]
MacNeil Workpaper 1b – GRID AC Thermal [PROPRIETARY]
MacNeil Workpaper 2a – GRID AC Tracking Solar [PROPRIETARY]
MacNeil Workpaper 2b – GRID AC Tracking Solar [PROPRIETARY]
MacNeil Workpaper 3a – GRID AC Wind [PROPRIETARY]
MacNeil Workpaper 3b – GRID AC Wind [PROPRIETARY]
MacNeil Workpaper 4a – GRID AC Fixed Solar [PROPRIETARY]
MacNeil Workpaper 4b – GRID AC Fixed Solar [PROPRIETARY]
MacNeil Workpaper – PDDRR [PROPRIETARY]
October 31, 2017 Rebuttal Testimony of Cheryl Murray from the Office of Consumer Services
Certificate of Service
October 31, 2017 Rebuttal Testimony of Abdinasir M. Abdulle, Ph.D. from Division of Public Utilities
Certificate of Service
October 30, 2017 Comments from the Division of Public Utilities
October 23, 2017 Memorandum Granting Extension of Time
October 23, 2017 Comments from the Division of Public Utilities
October 4, 2017 Amended Action Request Due: October 23, 2017
October 4, 2017 Rocky Mountain Power Schedule 37 Technical Conference Presentation from August 31, 2017
October 3, 2017 Direct Testimony of Cheryl Murray for the Office of Consumer Services
Certificate of Service
October 3, 2017 Direct Testimony of Neal Townsend for the Renewable Energy Coalition

Direct Testimony of John Lowe for the Renewable Energy Coalition
Exhibit A – Oregon Standard Avoided Cost Rates
October 3, 2017 Direct Testimony of Ken Dragoon on behalf of Utah Clean Energy

Direct Testimony of Kate Bowman on behalf of Utah Clean Energy
Certificate of Service
October 3, 2017 Direct Testimony of Abdinasir M. Abdulle, Ph.D. for the Division of Public Utilities
Certificate of Service
October 2, 2017 Action Request Due: November 1, 2017
October 2, 2017 Rocky Mountain Power Q2 Compliance Filing
RMP Appendix B.1 Avoided Cost Prices
RMP Appendix B.2 Table 2 Avoided Energy Costs
RMP Appendix B.3 – Avoided Cost Prices
RMP Appendix C – Utah Quarterly Compliance Filing Step Study
RMP Wkpr 1 (UT 2017.Q2 – FOT Partial Displacement)
RMP Wkpr 2 (QF Queue Partial Displacement Calculation)
September 21, 2017 Order Granting Intervention of Utah Clean Energy
September 18, 2017 Appendix A Re: Ken Dragoon
August 31, 2017 Appendix A Re: Emma Rieves
August 31, 2017 Audio File of Technical Conference held August 31, 2017
Sign-In Sheet
August 31, 2017 Appendix A Re: Sarah Wright, Kate Bowman, and Sophie Hayes
August 31, 2017 Utah Clean Energy Petition to Intervene
Certificate of Service
August 23, 2017 Public Service Commission Staff Questions for Avoided Cost Technical Conference
August 17, 2017 Direct Testimony of Daniel J. MacNeil for Rocky Mountain Power
Appendix 1 – AC Study Summary
Workpapers – Avoided Cost Study – Solar F
Workpapers – Avoided Cost Study – Solar T
Workpapers – Avoided Cost Study – Solar T D21W
Workpapers – Avoided Cost Study – Solar T D21W PTCAdj
Workpapers – Avoided Cost Study – Thermal
Workpapers – Avoided Cost Study – Thermal D21W
Workpapers – Avoided Cost Study – Thermal D21W PTCAdj
Workpapers – Avoided Cost Study – Wind
Workpapers – Avoided Cost Study – Wind D21W
Workpapers – Avoided Cost Study – Wind D21W PTCAdj
Workpapers – QF Pricing Detail – Solar F
Workpapers – QF Pricing Detail Solar T
Workpapers – QF Pricing Detail – Thermal
Workpapers – QF Pricing Detail – Wind
Workpapers – Schedule 37 Avoided Cost Study
Workpapers – 2017 IRP Table 1.2-3
Workpapers – Testimony Support
Workpapers – 1a – GRID AC Thermal [PROPRIETARY]
Workpapers – 1a – GRID AC Thermal D21W [PROPRIETARY]
Workpapers – 1b – GRID AC Thermal [PROPRIETARY]
Workpapers – 1b – GRID AC Thermal D21W [PROPRIETARY]
Workpapers – 2a – GRID AC Tracking Solar [PROPRIETARY]
Workpapers – 2a – GRID AC Tracking Solar D21W [PROPRIETARY]
Workpapers – 2b – GRID AC Tracking Solar [PROPRIETARY]
Workpapers – 2b – GRID AC Tracking Solar D21W [PROPRIETARY]
Workpapers – 3a – GRID AC Wind [PROPRIETARY]
Workpapers – 3a – GRID AC Wind D21W [PROPRIETARY]
Workpapers – 3b – GRID AC Wind [PROPRIETARY]
Workpapers – 3b – GRID AC Wind D21W [PROPRIETARY]
Workpapers – 4a – GRID AC Fixed Solar [PROPRIETARY]
Workpapers – 4b – GRID AC Fixed Solar [PROPRIETARY]
Workpapers – Capacity Contribution [PROPRIETARY]
July 27, 2017 Order Consolidating Dockets and Suspending the Phase II Schedule in Docket 17-035-T07, and Scheduling Order
July 26, 2017 Scheduling Conference Sign-in Sheet
July 21, 2017 Notice of Filing and Request to Make any Objection Thereto Known
July 19, 2017 Notice of Scheduling Conference
July 12, 2017 sPower’s Notice of Challenge and Request for Scheduling Conference
July 12, 2017 Comments from the Division of Public Utilities
July 12, 2017 Utah Clean Energy Notice of Challenge and Request for Scheduling Conference
June 26, 2017 Amended Action Request, Due: July 12, 2017
June 21, 2017 Action Request, Due: July 21, 2017
June 21, 2017 Quarterly Compliance Filing – 2017.Q1 Avoided Cost Input Changes
Exhibit A – RMP Appendix B.1
Exhibit B – RMP Appendix B.2
Exhibit C – RMP Appendix B.3
Exhibit D – RMP Appendix C
Workpapers – UT 2017.Q1 – FOT Partial Displacement
Workpapers – UT 2017.Q1 – QF Queue & Partial Displacement Calculation

Share this: