Docket No: 24-035-36

Rocky Mountain Power’s 2024 Net Metering and Interconnection Report

For questions regarding documents not linked call 801-530-6716

Date Description
September 5, 2024 Acknowledgment Letter from the Public Service Commission
August 2, 2024 Comments from the Division of Public Utilities
July 3, 2024 Notice of Filing and Comment Period
July 2, 2024 Action Request, Due: July 31, 2024
July 1, 2024 Rocky Mountain Power’s 2024 Net Metering and Interconnection Report for the Period April 1, 2023 through March 31, 2024
RMP Attachment A – Detail for Each Interconnected Customer-Owned Generation, Including Expired Credits
RMP Attachment B – Calculation to Support the Valuation of the Schedule 135 Expired Excess Generation Credits
RMP Attachment C – Customer Generation Summary Report
RMP Attachment D – Additional Detail for New Customers Who Have Interconnected on Schedule 135 or 136 During the Reporting Period
RMP Workpapers 1 – Credits Report