Docket No: 23-035-46

Application of Rocky Mountain Power for Approval of an Amendment to the Power Purchase Agreement between PacifiCorp and Kennecott Utah Copper LLC – Refinery

For questions regarding documents not linked call 801-530-6716

Date Description
December 14, 2023 Reporter’s Transcript, Re: November 30, 2023
December 13, 2023 Order Approving Amendments to Qualifying Facility Power Purchase Agreements
November 30, 2023 Recorded Live Stream of Virtual Hearing Held November 30, 2023
November 9, 2023 Comments from the Division of Public Utilities
October 12, 2023 Scheduling Order and Notice of Virtual Hearing
September 28, 2023 Notice of Virtual Consolidated Scheduling Conference
September 27, 2023 Action Request, Due: October 27, 2023
September 27, 2023 Rocky Mountain Power’s Application
RMP Exhibit A – Fourth Amendment to Non-Firm Power Purchase Agreement [CONFIDENTIAL]
RMP Workpapers 1 – 2023 Qualifying Facility Pricing Detail
RMP Workpapers 2 – 2023 Avoided Cost Study
RMP Workpapers 3 – 2023 Line Loss Adjustment [CONFIDENTIAL]
RMP Workpapers 4 – 2023 GRID Avoided Cost Study NPC [CONFIDENTIAL]
RMP Workpapers 5 – 2023 GRID Avoided Cost Study BASE [CONFIDENTIAL]

Share this: