Date |
Description |
October 25, 2021 |
Appendix A, Re: Leah J. Wellborn for the Office of Consumer Services |
October 15, 2021 |
Order Granting Request for Final Shortlist Report |
October 4, 2021 |
Notice of Request and Expedited Period to Respond |
October 4, 2021 |
Rocky Mountain Power’s Request for Final Shortlist Report |
September 3, 2021 |
Notice |
September 2, 2021 |
Redacted Shortlist Report of the Independent Evaluator, Merrimack Energy Group, Inc.
Shortlist Report of the Independent Evaluator, Merrimack Energy Group, Inc. [HIGHLY CONFIDENTIAL]
Appendix A – Summary of Bids Submitted by Bidder and Technology [HIGHLY CONFIDENTIAL]
Appendix B – List of Non-Compliant Bids [HIGHLY CONFIDENTIAL]
Appendix C – List of Projects with Executed LGIAs [HIGHLY CONFIDENTIAL]
Appendix D – Utah Summary of Solar Project Evaluation Results [HIGHLY CONFIDENTIAL]
Appendix E – Utah Summary of Solar and Storage Evaluation Results [HIGHLY CONFIDENTIAL]
Appendix F – 2020 AS RFP ISL Analysis [HIGHLY CONFIDENTIAL]
Appendix G – Best and Final Offers and Metrics [HIGHLY CONFIDENTIAL]
Appendix H – Comparison of Rock Creek 1 and 2, PPA and BTA [HIGHLY CONFIDENTIAL] |
July 17, 2020 |
Order Approving 2020 All Source RFP |
July 6, 2020 |
Rocky Mountain Power’s Notice of Final 2020 All Source Request for Proposals |
July 2, 2020 |
Notice of Decision |
June 29, 2020 |
Rocky Mountain Power’s Corrected Filing |
June 29, 2020 |
Order Granting Intervention of the School and Institutional Trust Lands Administration |
June 18, 2020 |
Rocky Mountain Power’s Supplemental Reply |
June 15, 2020 |
Reply Comments of Interwest Energy Alliance |
June 15, 2020 |
Utah Clean Energy’s Reply Comments |
June 15, 2020 |
Reply Comments of the Utah Association of Energy Users on PacifiCorp’s Proposed Solicitation Process |
June 15, 2020 |
Rocky Mountain Power’s Reply in Support of Application for Approval of Solicitation Process RMP Appendix A RMP Appendix C RMP Appendix E RMP Appendix F |
June 15, 2020 |
Reply Comments from the Office of Consumer Services |
June 12, 2020 |
Reply Comments from the Division of Public Utilities |
June 12, 2020 |
Order Granting Intervention of Utah Clean Energy |
June 8, 2020 |
Petition to Intervene of the School and Institutional Trust Lands Administration |
June 3, 2020 |
Task A7 Report of the Utah Independent Evaluator, Regarding PacifiCorp’s Draft All Source Request for Proposals (2020AS RFP) |
June 1, 2020 |
Appendix A, Re: Hunter Holman and Sarah Wright for Utah Clean Energy |
May 28, 2020 |
Order Granting Intervention of the Interwest Energy Alliance |
May 22, 2020 |
Utah Clean Energy’s Petition for Leave to Intervene |
May 22, 2020 |
Initial Comments of Interwest Energy Alliance |
May 22, 2020 |
Initial Comments of the Utah Association of Energy Users on PacifiCorp’s Proposed Solicitation Process |
May 22, 2020 |
Comments from the Office of Consumer Services OCS Attachment 1 – OCS Data Requests |
May 21, 2020 |
Comments from the Division of Public Utilities |
May 19, 2020 |
Rocky Mountain Power’s Supplemental Filing |
May 18, 2020 |
Order Granting Intervention of the Utah Association of Energy Users |
May 15, 2020 |
Correspondence from Gary L. Widerburg |
May 6, 2020 |
The Interwest Energy Alliance’s Motion for Permission to be Represented by Out-Of-State Attorney |
May 6, 2020 |
The Interwest Energy Alliance’s Petition to Intervene |
May 4, 2020 |
Scheduling Order |
April 27, 2020 |
Appendix A, Re: Phillip J. Russell for the Utah Association of Energy Users |
April 27, 2020 |
Petition to Intervene of the Utah Association of Energy Users |
April 22, 2020 |
Rocky Mountain Power’s Submission of Additional Exhibit RMP BWG-1 E3 to its Application |
April 14, 2020 |
Appendix A, Re: Wayne Oliver and Keith Oliver for Merrimack Energy Group, Inc. |
April 14, 2020 |
Appendix A, Re: Brian R. Barber, Philip Hayet, and Samuel Wyrobeck for the Office of Consumer Services |
April 13, 2020 |
Notice of Telephonic Scheduling Conference |
April 10, 2020 |
Action Request, Due: May 11, 2020 |
April 9, 2020 |
Application for Approval of Solicitation Process
Appendix A: Attachment 1A – Project Document Formatting and Requirements Attachment 1B – Document Deliverables General AutoCAD Drafting Standards Spec DCAP876 EBU PX-S01-S01A Substation Equipment Power Transformer EBU PX-S02 Substation Equipment ZS-102 Two-Winding Dist. Transformer Specification EBU SI-S04 Electrical Equipment Insulating Oil EBU SI-S02 Wind, Ice, and Seismic Withstand EBU SI-S03 Contaminated Environment Protection Procedure SP-TRF-INST Transformer Installation TD051 Danger Sign Engineering Handbook Part 6B 5 Fence Application and Construction Section 02810 Chain Link Fencing and Gates Section 02815 Cantilever Slide Gate Engineering Handbook Part 6B 6 Substation Grounding GEN-ENG-RELAY-0001 Protective Relaying Requirements for New Plants GEN-ENG-RELAY-0002 Arc Flash Requirements for New Plants GEN-ENG-RELAY-003 CT and PT Integrity Test GEN-ENG-RELAY-1003 Protective Relay Maintenance and Testing PRC 005 Relay Installation Procedure GPCPEQPMNTINST Current Transformer Installation Procedure GPCPCTINST Current Transformer Installation Form GPCFCTINST SG001 Substation High Voltage Warning Signs Exhibit Xv4 Substation Equipment Installation SV 251 Bird and Animal Protection for Miscellaneous Equipment SV 001 Bird and Animal Protection General Information SV 002 Bird and Animal Protection General Installation Instructions RFP Appendix A.1 Solar Specifications RFP Appendix A.1 Wind Scope of Work RFP Appendix A.2 Wind Definitions RFP Appendix A.3 Wind Specifications RFP Appendix A Battery Storage Tech Specifications RFP Appendix A-2 Interconnection Agreement RFP Appendix A-3 Permit Matrix RFP Appendix A-5 Project Single Line Drawings and Layouts RFP Appendix A-6 Division of Responsibilities RFP Appendix A-9 Product Data Equipment Supply Matrix RFP Appendix A-10 Plant Performance Guarantee Warranties Volume 8 Consultant Drafting Procedures and Standards for Engineering Drawings
Appendix C
Appendix E: RFP Appendix E-2 Form of PPA Resource Only RFP Appendix E-2 Form of PPA Resource Only (2) RFP Appendix E-2 Form of PPA Resource Plus BESS RFP Appendix E-2 Form of PPA Resource Plus BESS (2)
Appendix F: Appendix F-2 BTA Term Sheet Appendix F-2 BTA Term Sheet (2)
Appendix K
|
March 31, 2020 |
Notice of Change of Firm Name |
January 23, 2020 |
Notice of 2020 All Source Request for Proposals |
Share this: