Docket No: 18-035-36

Application of Rocky Mountain Power for Authority to Change its Depreciation Rates Effective January 1, 2021

For questions regarding documents not linked call 801-530-6714

Date Description
September 13, 2018 Notice of Scheduling Conference
September 13, 2018 Comments from the Division of Public Utilities
September 12, 2018 Appendix A, Re: William Dunkel and Roxie McCullar for the Division of Public Utilities
September 11, 2018 Action Request, Due: October 11, 2018
September 11, 2018 Rocky Mountain Power’s Application
RMP Spanos Workpapers 1 – 2017 Depreciation Schedule East Plant
RMP Spanos Workpapers 2 – 2017 Depreciation Schedule West Plant
RMP Spanos Workpapers 3 – 2017 Production Net Salvage East Plant
RMP Spanos Workpapers 4 – 2017 Production Net Salvage West Plant
RMP Spanos Workpapers 5 – 2020 Depreciation Schedule East Plant
RMP Spanos Workpapers 6 – 2020 Depreciation Schedule West Plant
RMP Spanos Workpapers 7 – 2020 Production Net Salvage East Plant
RMP Spanos Workpapers 8 – 2020 Production Net Salvage West Plant
RMP Teply Workpapers 9 – Estimated Decommissioning Costs
RMP McDougal Workpapers 10 – Depreciation Rate Comparison
RMP Teply Exhibit A – Estimated Decommissioning Costs
RMP Teply Exhibit B – Estimated Plant Retirement Lives Steam and Gas
RMP McDougal Exhibit C – UT Allocated Edited
RMP McDougal Exhibit D – Estimated STEP Deferral and Amortization Table
RMP McDougal Exhibit E – BCC Balances
RMP Hemstreet Exhibit F – Existing and Proposed Depreciable Lives for Renewable Resources
RMP Spanos Exhibits Accompanying Testimony – Depreciation Study

Share this: