Docket No: 12-057-04
Lake Side Power Plant
Docket Index
Docket Number: 12-057-04
In the Matter of: the Application of Questar Gas Company to Provide Natural Gas Transportation Service to Serve the Lake Side Power Plant Facility
217986
For questions regarding documents not linked call 801-530-6714
| Date | Description |
|---|---|
| June 20, 2012 | Report and Order |
| June 14, 2012 | Reporter’s Transcript Re: June 6, 2012 |
| May 23, 2012 | Rebuttal Testimony of Barrie L. McKay [PROPRIETARY] |
| May 23, 2012 | Rebuttal Testimony of Eric Orton [PROPRIETARY] Certificate of Service |
| May 4, 2012 | Pre-Filed Confidential Direct Testimony of Marlin Barrow [PROPRIETARY] Certificate of Service Exhibit A [PROPRIETARY] Exhibit B [PROPRIETARY] Exhibit C [PROPRIETARY] |
| May 4, 2012 | Direct Testimony of Charles E. Peterson Certificate of Service Exhibit A – Resume of Charles E. Peterson Exhibit B [PROPRIETARY] |
| May 4, 2012 | Direct Testimony of Eric Orton [PROPRIETARY] Certificate of Service |
| April 26, 2012 | Order Granting Intervention of Utah Association of Energy Users |
| April 17, 2012 | Division of Public Utilities’ Notice of Substitution of Counsel |
| April 16, 2012 | Appendix A Re: Oliwia Smith, Neal Townsend, Kevin C. Higgins, Courtney Higgins, and Kelly Francone |
| April 6, 2012 | Petition to Intervene of the Utah Association of Energy Users |
| April 6, 2012 | Appendix A Re: Gary A. Dodge |
| April 4, 2012 | Order Granting Intervention of Rocky Mountain Power |
| April 3, 2012 | Correspondence from Gary L. Widerburg |
| March 27, 2012 | Comments from DPU |
| March 27, 2012 | Scheduling Order |
| March 16, 2012 | Comments from OCS |
| March 16, 2012 | Notice of Scheduling Conference |
| March 15, 2012 | Motion to Intervene |
| March 14, 2012 | Comments from DPU |
| March 8, 2012 | Action Request Due: April 6, 2012 |
| March 2, 2012 | Application Direct Testimony of Barrie L. McKay [PROPRIETARY] Exhibit A – Qualification of Barrie L. McKay [PROPRIETARY] Exhibit B – Agreement [PROPRIETARY] Exhibit C – Engineers Estimate of Cost [PROPRIETARY] Exhibit D – Revenue Requirement [PROPRIETARY] Exhibit E – Schematic [PROPRIETARY] |